Concrete Waste Factor

Last updated November 13, 2026

Order 5% to 10% more concrete than the calculated volume. The extra covers uneven ground, forms that bow, spillage and what is left in the mixer or the pump.

How much to add

SituationWaste allowance
Flat, well-formed slab on a compacted base5%
Typical slab or sidewalk10%
Earth-formed footing or trench10% to 15%
Curved or irregular shapes10% to 15%
Pumped concreteAsk the pump operator; some is left in the line

What the allowance looks like in yards

Calculated volume+5%+10%+15%
1 yd³1.051.101.15
2 yd³2.102.202.30
3 yd³3.153.303.45
5 yd³5.255.505.75
8 yd³8.408.809.20

Where the extra goes

  • Uneven subgrade: a base that is half an inch low across a 4 inch slab uses 12.5% more concrete.
  • Form movement: forms bow outward under the weight of wet concrete.
  • Spillage and handling: wheelbarrows, chutes and tools all carry some away.
  • Rounding: ready-mix is sold in quarter yards and bags are whole, so you round up anyway.

Every calculator on this site has a waste slider set to 10%. Start with the concrete calculator.

Frequently asked questions

How much extra concrete should I order?

Add 5% to 10% for most jobs. Use 10% or more on rough ground, in earth-formed trenches or for curved shapes.

What happens if I run short?

The first concrete starts to set before the rest arrives, which leaves a weak line called a cold joint. A second small delivery also costs more than a few extra bags or a slightly larger first order.

What do I do with leftover concrete?

Have a small form ready, such as a stepping stone or a pad for a trash can, so leftover concrete is not wasted.